I-55 Corridor Transportation and Growth Management Plan


Click Map for pdf of I-55 Plan
Additional Reference Materials may be found in the Resource Library

Frequently Asked Questions regarding the I-55 Corridor Plan

What is the I-55 Corridor Transportation & Growth Management Plan?

The I-55 Corridor Transportation & Growth Management Plan is an intergovernmental plan between Madison County, the City of Edwardsville, and the Village of Glen Carbon to plan for future land use in the I-55 corridor area. A comprehensive, coordinated strategy is necessary to ensure development within the corridor area is in line with the plans of the individual governmental entities. The projected growth in this area calls for a plan of this caliber to foster strategic, controlled growth within this portion of Madison County.

The I-55 Corridor Plan is intended to serve as a blueprint and guide for elected officials in Edwardsville, Glen Carbon and Madison County to set policies and develop strategies to be prepared for inevitable growth and development in the area bordering Interstate 55 over the next 20-plus years.

The I-55 Corridor Plan is not the county's zoning map. While this has been adopted by the county, the village and the city as part of their comprehensive plans, it does not designate affected lands into zoning districts.

Why was the I-55 Corridor Plan initiated?

In the year 2000, Madison County adopted a comprehensive zoning plan known as the 2020 Madison County Land Use and Resource Management Plan. This plan designated the I-55 Corridor as a part of the Bluffs Corridor. The 2020 Plan refers to the Bluffs Corridor as rapidly changing, and as the area of the county that had experienced the greatest population increase over the past twenty years. The 2020 Plan notes that a significant amount of land in the Bluffs Corridor transitioned from agricultural to residential use, and calls for the anticipation of aggressive residential growth.

As a result of the 2020 Plan, the county participated in the preparation of, and adopted, Phase I of the I-55 Corridor Plan as an amendment to its comprehensive zoning plan, the 2020 Plan.

Growth and development in the communities of Edwardsville and Glen Carbon, and in outlying Madison County, continues to be strong. A substantial amount of this development is occurring east of Route 159, toward Interstate 55. There is concern among local government officials that their current comprehensive plans do not address many of the issues associated with growth and development. These issues include how new roads will be planned and interconnected, which areas are to be reserved for parks and open space, what areas are best suited for residential, commercial, and mixed uses, and how the communities can work collectively to provide essential public services.

Who are the key players in the I-55 Plan Project?

Plan Management Team: The Plan Management Team (PMT) consists of representatives from the City of Edwardsville, Village of Glen Carbon, and Madison County. These members include municipal employees as well as business leaders in the community. The PMT has worked together since the plan's conception, obtaining public input, guiding the planning process, creating goals and narrowing the focus of the plan.

Madison County, City of Edwardsville and Village of Glen Carbon:

These three governmental entities have the legal authority to enact land-use ordinances in their respective territories of the I-55 Plan area. Madison County has legal authority over all the unincorporated areas within the County. However, as provided by state statutes, Edwardsville and Glen Carbon also share authority with the County over land subdivision within 1.5 miles of their respective corporate limits in unincorporated areas.

The planning commissions of the county, city and village have been assigned the responsibility of working with the consultant team(s) involved in the project, in order to review plans and make recommendations to their respective governing bodies for formal action.

The Alliance of Edwardsville and Glen Carbon: The Alliance of Edwardsville and Glen Carbon is a not-for-profit, public-private partnership that serves as an economic development organization for Edwardsville and Glen Carbon. The Alliance's role is the facilitation and management of the I-55 Plan. The Alliance does not have the authority to make decisions regarding land use in the I-55 area.

Pin Oak Township: The majority of the approximately 30 square miles encompassing the I-55 Corridor Plan lies within the boundaries of Pin Oak Township. As such, township officials have been updated throughout the course of completing the I-55 Corridor Plan. As noted above, townships do not have legal authority to legislate land use regulations and zoning. This authority is shared with Madison County for territory located in unincorporated areas, and with the City of Edwardsville and Village of Glen Carbon for property located within their respective municipal limits and 1.5 miles out of their respective corporate limits. Pin Oak Township is represented on the Madison County Board, which unanimously voted to approve the adoption of the I-55 Corridor Plan as a part of the comprehensive plan for this unincorporated part of the county. We continue to work closely with Pin Oak Township officials on the status of the plan and are addressing concerns of their constituents.

I own property in the I-55 Plan area. How will I be affected?

The plan is a long-range blueprint that each governmental entity uses to guide future development. The Plan will also be referenced when the rezoning of property is proposed, either by the current landowner or potential developer. Property owners are required to be notified of any actions that could change the zoning status of their property, and will be given an opportunity to provide input before action is taken.

Will I be forced to sell my property?

Several questions were raised at the informational meetings and regarding property rights, particularly the use of eminent domain.

Land sales in the I-55 corridor area are, and will continue to be, a private matter between a willing property owner and a prospective buyer. Eminent domain is only used as a last resort by governmental entities that desire to acquire land for public use, usually in the form of roadway and infrastructure projects. Only certain governmental entities have the authority to acquire property through eminent domain for projects that meet the definition of "public use." Historically, eminent domain has been used primarily for acquisition of privately held property needed for roadway and infrastructure-related projects, as opposed to private developments. In such instances, every effort is made to negotiate the market purchase price (fair market value) with the affected property owners. Eminent domain is normally used as the last resort, and only when it absolutely necessary to acquire land for public use. Developers looking to assemble land for projects are not legally eligible to use the powers of eminent domain.

What is annexation?

Annexation is the incorporation of a piece of property into an existing incorporated entity, such as a city. Property owners often petition for annexation to gain municipal benefits. Additionally, annexation is used by municipalities in order to manage expansion in an orderly manner. When territories are annexed by a municipality, they become a part of that municipality's service area, providing for services such as police protection, water and sewer, and street maintenance.

What is the annexation process?

The annexation process requires that property owners file a petition for consideration and approval with either the City Council or Village Board. Annexation may only be forced if the area to be annexed is smaller than 60 acres, and is surrounded by one or more incorporated entities. However, just because property is surrounded by one or more municipalities does not necessarily mean that the property will be involuntarily annexed. Any questions should be referred to your personal attorney.

How were the new roads and interchange locations chosen, and when will they be completed?

A major component of Phase I of the I-55 Corridor Plan involved creating a "concept plan" for future roads and new interchanges to I-55 and I-270. A critical element in accommodating future growth and development is planning for a transportation network to handle the expected traffic loads as the area develops. Existing topography, connectivity to existing roadways, current development, the configuration of land ownership, and transportation standards were considered in planning for future roadway corridors.

The areas designated for future interstate interchanges were reviewed in relation to current highway standards, and in consultation with representatives of the Illinois Department of Transportation (IDOT). There is not a firm timeframe for completing new roads and interchanges. Timing of the completion is largely linked to the occurrence of new development. The I-55 Corridor Plan will enable developers to determine how their projects will be planned in relation to new roads and the right-of-way (ROW) needed to complete the arterial and collector roadways.

New interstate interchanges are long-range construction projects that require approval from the Federal Highway Administration and completion of an extensive planning and approval process involving environmental, socioeconomic, geometric, access and traffic studies. Funding for interchanges is very expensive and will require being included on IDOT's long-range transportation improvements plan.

What is the timeframe for completing the improvements?

The I-55 Corridor Plan is "market driven." Development is largely dependent upon economic conditions and other factors that impact the continued viability of our area. It is difficult to determine which areas will be developed first. Funding and the timing of public infrastructure projects—such as the completion of Governors' Parkway and the extension of water and sewer—can influence the pace at which private-sector development will occur.

Are there provisions for modifying the I-55 Corridor Plan after it is adopted?

The I-55 Corridor Plan is a long-range vision of how the area could evolve over the next 20+ years. As such, it is extremely difficult to project how growth will occur, and to predict economic changes that could impact the overall development. It should be emphasized that the I-55 Corridor Plan is a "concept" plan that is subject to change and modification.

The governmental entities have the ultimate authority for making adjustments to the plan as they see fit.

What is meant by "Phase I" and "Phase II"?

Phase I:

The HOK Planning Group of St. Louis was contracted as the principal consultant group for Phase I of the I-55 Corridor Plan, and HOK worked closely with local government officials, as well as businesses and community leaders, throughout the course of the project. A major component of the plan is a market and economic analysis that was performed by Development Strategies, Inc., which included an evaluation of the present market, economic conditions, and strategies to brand the corridor as a superior knowledge-based employment center. The evaluation also recommended actions to attract new commercial development to the area.

The planning process was intentionally designed to maximize public input and participation at all levels, and throughout each stage of the project. There were numerous public informational meetings held to provide an opportunity for public input. The meetings were held at Liberty Middle School in Edwardsville on the following dates:

• November 24, 2003

• February 19, 2004

• April 15, 2004

• May 11, 2004

• July 8, 2004

Those attending the meetings were asked to evaluate various planning concepts, review the land-use/development scenarios presented by the consultants, complete surveys to describe what type of land-use pattern was appropriate for the corridor, rate several land-use components, and indicate the preferred development scenarios. The consultant and Plan Management Team took the public comments into consideration in preparing the final concept plan. In addition to these meetings, meetings for public officials were held at The Alliance's office in November of 2003, and in February, April and June of 2004. A public hearing was held by the Edwardsville, Glen Carbon, and Madison County Plan Commissions in April of 2005.

The I-55 Corridor Plan was adopted in 2005 by the City of Edwardsville, Village of Glen Carbon and Madison County and will be used by the respective jurisdictions in considering requests for new development, zoning changes, planning for infrastructure projects, transportation networks and land use within the 30 + square-mile area.

Phase II:

A $150,000 grant through the Illinois Department of Transportation has been secured and will be used, along with a local funding amount of $15,000, to advance many of the recommendations as outlined in the Phase I of the I-55 Corridor Plan. Phase II of the I-55 Corridor project will build on the coalition between Madison County, the City of Edwardsville and the Village of Glen Carbon to address growth-related issues that transect across the corporate boundaries. Other critical local governmental partners include Edwardsville Township, Pin Oak Township and the Edwardsville and Triad School Districts, which are impacted by the continued residential growth of the planning area.

The scope of work for Phase II includes the following components:

1. Transportation & Infrastructure Planning

A principal work element of the initial I-55 Corridor Plan included an analysis of the
existing transportation network serving the study area, and identified potential new roads that would eventually need to be constructed to facilitate the planned development. While the plan delineated a "general location" for new roads, connections to existing roads and proposed interchanges, a greater level of planning is needed to proceed with formal legislative measures to acquire and preserve the right-of-way for planned roadway projects.

2. Land Use Regulation/Legislation

Phase I included recommended actions at the local governmental level with regard to legislative issues (i.e. zoning, design standards, etc.) to help guide future land use to conform to the concept plan.

The major task in this component of Phase II will be to research land use development codes and regulatory measures that promote the land-use concepts that were recommended in Phase I. Development and adoption of uniform code standards that would complement the growth management plan will be a critical element of the overall project.

3. Detailed Development Plans

Phase I recognized certain strategic areas where unique mixed-use development, such as town centers and walkable neighborhoods, should be encouraged. Based on the conceptual land use plan, the project will entail developing refined conceptual plans.

4. Public Open Space

One of the principal project goals as outlined in Phase I is "to encourage orderly and sound development to preserve land for open space." Throughout the course of developing the I-55 Corridor Plan, the need to preserve open space was brought up as a major concern by the public at the informational meetings. The strategies defined in the I-55 Plan include expanding the network of open space through the use of existing roads, and integrating open space and buffering along proposed roadways and transportation corridors. This would create a series of "greenways" and parks connecting neighborhoods, as well as major employment centers.

Phase II will look at specific areas that should be considered for retention as open spaces. Additionally, the project will advance the planning of the Silver Creek area to identify specific methods to protect the area from encroaching development.

5. Economic Development Strategy

A key component included in Phase I was an overview of the economic analysis of the area in context with the greater St. Louis region. The consultant team noted the attractiveness of certain nodes along the I-55 Corridor that may be suitable for the location of regional professional offices. The target for economic development efforts in this area continues to be knowledge-intensive businesses. This component will address specific strategies to attract new economic investments to the developing I-55 Corridor area.

Another important element of this plan will include the effective presentation of the identified capabilities of the I-55 Corridor to businesses and governments, identifying investors that will produce the desired knowledge-intensive jobs.

6. Education

Critical to the success of advancing the recommendations and moving the I-55 Plan toward implementation is making public-sector officials aware of the plan's key components. These officials will be responsible for adopting the plan and initiating policies to see that the plan is executed. Additionally, we recognize the importance of strengthening alliances with the development community (i.e. developers, builders, realtors, landowners), which needs to have a better understanding of the overall long-term vision for the I-55 Corridor. Their understanding is paramount in order to ensure success in sustainable development. This educational component will be designed to link the public sector with the private sector.

The Plan Management Team will solicit proposals from professional consulting firms that will be contracted to provide services to complete the major components as highlighted above.

 

I-55 Updates
RFP for Phase II has been submitted to the consultants who responded to the Phase II RFQ.

 